The fixed overhead is an allocated common cost. how much is the relevant cost of the wicket?

   10

Answers

@jhonny answered 1 month ago.

 The Fixed Overhead is an allocated common cost. How much is the relevant cost of the Wicket? https://www.linkedin.

   00

Replies to this Answer

No reply yet.

@issue answered 1 month ago.

 The fixed overhead is an allocated common cost. how much is the relevant cost of the wicket? The relevant cost is the direct cost plus the allocated common cost. The direct cost is $20. The allocated common cost is $7. The relevant cost is $20 + $7 = $27.